There were eight responses to the consultation, of which five supported the proposed decommissioning. DCC is now recommending that the Draft Requesting Party Decommissioning Timetable be approved by the Secretary of State. This would result in final migrations in the MOC (Secure) cohort completing week commencing 22nd September 2025.
DCC remains committed to the completion of migrations and is working with Parties to maximise migration volume. We encourage all Parties to submit Migration Authorisations for any meters that remain eligible for enrolment, including those operated at split sites.
Alongside the conclusion document we have also provided a copy of our recommendation letter sent to the Department for Energy Security and Net Zero